Project roles table
A project roles table is a planning tool that is included as part of the RIBA Plan of Work Toolbox. It takes the form of a table that sets out the roles required on a project as well as defining the stages during which those roles are required and the parties responsible for carrying out the roles. Ref https://www.ribaplanofwork.com/Help/Glossary.aspx
It is often used in association with a design responsibility matrix which sets out responsibility for each element of the design at each stage of the design development process and to what level of detail. For more information, see Design responsibility matrix.
A project roles table might also be accompanied by a contractual tree, illustrating the contractual relationship between the participants in the project. For more information, see Contractual tree.
A project roles table typically takes the form of a bar chart with the various project roles listed on the y-axis and the numbered projects stages on the x-axis. A bar extends along the x-axis to represent the stages of work that the particular role is responsible for.
Alternatively, it can take the form of a table which uses a RACI matrix. This is a form of form of responsibility assignment matrix (RAM) that can be used to help systematically manage a process or project. RACI sets out for each activity at each stage whether the various parties on the project are Responsible, Accountable, should be Consulted, or just kept Informed. For more information see: RACI matrix.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.